Recently Issued Air Discharge Permits

Facilities are listed in alphabetical order by final permit date.

These permits have been recently issued final by the Southwest Clean Air Agency. These permits are open for appeal to the Pollution Control Hearing Board until 30 days after the date the permit was issued as shown below. For information on the appeals process, click here.

Nutter Corporation - Vancouver  
Application Notice:  CL-3091
Date Permit Posted to Web:  Tuesday, July 30, 2019
Date Final: Monday, July 29, 2019
Appeal Period Ends:  Wednesday, August 28, 2019
Agency Contact: Clint Lamoreaux, 360-574-3058 ext. 131
Air Discharge Permit: 19-3349ADP.PDF
Technical Support Document: 19-3349TSD.PDF  
SEPA Lead Agency: Cowlitz County
SEPA Checklist Date: Saturday, August 20, 2016
SEPA Checklist: VIEW
SEPA Action: SEPA-DNS
SEPA Register/Newspaper Notice: None 
SEPA Final Date: Thursday, March 09, 2017
SEPA Determination: VIEW
Notes: Installation and operation of a portable/mobile Terex Powerscreen 1000SR cone crusher - track mounted with a non-road diesel engine 350 BHP and a Terex Powerscreen Warrior 1800 2 deck incline screen on tracks powered by a nonroad diesel engine and a Deutz engine powered conveyor
 
Ocean Beach Chevron - Longview  
Application Notice:  CO-1013
Date Permit Posted to Web:  Friday, August 09, 2019
Date Final: Monday, August 05, 2019
Appeal Period Ends:  Wednesday, September 04, 2019
Agency Contact: Clint Lamoreaux, 360-574-3058 ext. 131
Air Discharge Permit: 19-3353ADP.PDF
Technical Support Document: 19-3353TSD.PDF  
SEPA Lead Agency: SWCAA
SEPA Comments Due By: Monday, August 05, 2019
SEPA Checklist: None
SEPA Action: SEPA-EXEMPT
SEPA Register/Newspaper Notice: None 
SEPA Final Date: Monday, August 05, 2019
SEPA Determination: VIEW
Notes: Removal of Stage II gasoline vapor recovery euipment as facility is no longer above threshold to require Stage II
 
Pacific Crest Building Supply, Inc. - Ridgefield  
Application Notice:  CL-3081
Date Permit Posted to Web:  Tuesday, July 30, 2019
Date Final: Thursday, July 25, 2019
Appeal Period Ends:  Saturday, August 24, 2019
Agency Contact: Vannessa McClelland, 360-574-3058 ext. 129
Air Discharge Permit: 19-3317R1ADP.PDF
Technical Support Document: 19-3317R1TSD.PDF  
SEPA Lead Agency: SWCAA
SEPA Comments Due By: Thursday, July 25, 2019
SEPA Checklist: None
SEPA Action: SEPA-EXEMPT
SEPA Register/Newspaper Notice: None 
SEPA Final Date: Thursday, July 25, 2019
SEPA Determination: VIEW
Notes: Request to add a Rohner spray booth - Stain Booth - back into the permit that was removed during the last permit revision.
 
Royal Van 76 - Vancouver  
Application Notice:  CL-3083
Date Permit Posted to Web:  Tuesday, August 13, 2019
Date Final: Monday, August 05, 2019
Appeal Period Ends:  Wednesday, September 04, 2019
Agency Contact: Clint Lamoreaux, 360-574-3058 ext. 131
Air Discharge Permit: 19-3352ADP.PDF
Technical Support Document: 19-3352TSD.PDF  
SEPA Lead Agency: SWCAA
SEPA Comments Due By: Monday, August 05, 2019
SEPA Checklist: None
SEPA Action: SEPA-EXEMPT
SEPA Register/Newspaper Notice: None 
SEPA Final Date: Monday, August 05, 2019
SEPA Determination: VIEW
Notes: Less than 600,000 gal/yr throughput - removal of Stage II gasoline vapor control equipment - deactivation in place
 
Tapani, Inc. - Grinding - Vancouver  
Application Notice:  CL-3082
Date Permit Posted to Web:  Wednesday, July 31, 2019
Date Final: Wednesday, July 31, 2019
Appeal Period Ends:  Friday, August 30, 2019
Agency Contact: Wess Safford, 360-574-3058 ext. 126
Air Discharge Permit: 19-3350ADP.PDF
Technical Support Document: 19-3350TSD.PDF  
SEPA Lead Agency: SWCAA
SEPA Comments Due By: Wednesday, July 31, 2019
SEPA Checklist Date: Thursday, May 30, 2019
SEPA Checklist: VIEW
SEPA Action: SEPA-DNS
SEPA Register/Newspaper Notice: None 
SEPA Final Date: Wednesday, July 31, 2019
SEPA Determination: VIEW
Notes: Approval for operation of wood grinder, diesel engine, diesel engine powered conveyor and haul roads for wood grinding operations. NONROAD engines.
 
WaferTech LLC - Camas  
Application Notice:  CL-3078
Date Permit Posted to Web:  Friday, August 09, 2019
Date Final: Monday, August 05, 2019
Appeal Period Ends:  Wednesday, September 04, 2019
Agency Contact: John St.Clair, 360-574-3058 ext. 127
Air Discharge Permit: 19-3351ADP.PDF
Technical Support Document: 19-3351TSD.PDF  
SEPA Lead Agency: Port of Vancouver
SEPA Comments Due By: Monday, August 05, 2019
SEPA Checklist Date: Wednesday, April 17, 2019
SEPA Checklist: VIEW
SEPA Action: SEPA-DNS
SEPA Register/Newspaper Notice: None 
SEPA Final Date: Monday, August 05, 2019
SEPA Determination: VIEW
Notes: Revise existing permit to increase NOx emission limits for 1F1-SCR-01, -02, 03, -04, -15 due to test data and combined stacks for 1F2-SCR-01 and 02 and 1P5-SCR-01, -02